13.1 C
Canberra
Thursday, May 22, 2025

Canberra Liberals question SPIRE progress

Progress on the ACT Governmentโ€™s Surgical Procedures, Interventional Radiology and Emergency (SPIRE) Centre at the Canberra Hospital has come under fire from the Canberra Liberals.

Shadow Minister for Health Vicki Dunne has criticised the governmentโ€™s handling of the project, suggesting a series of failures including blown-out completion dates as well as logistical and budgetary bungles.

She said the ordeal also shows a โ€œlack of transparencyโ€ with much of the information โ€œuncovered through Freedom of Information requests or tender searches by the Canberra Liberals and the mediaโ€.

โ€œACT Laborโ€™s 2016 election commitment was a flash-in-the-pan response to the Canberra Liberalโ€™s commitment to redevelop buildings 2 and 3 at The Canberra Hospital, which Labor dismissed as unnecessary,โ€ Mrs Dunne said.

โ€œWhat we ended up with from ACT Labor was a back-of-the-drinks-coaster plan for SPIRE. The planned site for SPIRE has had to be relocated and re-scoped with new budgets set (which they wonโ€™t reveal), and now we learn that construction wonโ€™t start until 2021 with completion at a very ambitious 2023-24.

โ€œMeanwhile, there will be increasing capacity pressures in the emergency department, ICU and surgical theatres and beds.โ€

The ACT Government rejects the Canberra Liberalsโ€™ assertions regarding the SPIRE project.

According to an ACT Government spokesperson, the project is in its enabling works phase with preparatory works due to start this year.

โ€œIn order to free-up the site for the new emergency, surgical and critical care facility, a number of existing buildings must be vacated and demolished,โ€ the spokesperson said. โ€œThe plans for relocating the existing functions from these two buildings are well advanced and works will commence on the placement of a new temporary building later in 2019.โ€

It is expected that preparatory, demolition and temporary construction activities will take place over this year and next year.

โ€œThe subsequent construction of the new facility itself is scheduled to commence in late 2020/early 2021 following receipt of development approval,โ€ the spokesperson said. โ€œThe duration for construction is currently estimated at approximately three years and the new facility will be complete in 2023/24.โ€

ACT Minister for Health, Rachel Stephen-Smith, said SPIRE will be โ€œthe single largest investment in our health care system since self-government; this is a major project for the ACT Government and the Canberra regionโ€.

โ€œAn investment of this magnitude requires extensive engagement with stakeholders and clinicians. The ACT Government has taken the time needed to get the project right and to ensure weโ€™re delivering a facility that meets the needs of Canberrans now and into the future.โ€

For more:

More Stories

‘Not satisfied’: Brumbies ace eyes elusive Super crown

He's being touted as a Wallabies bolter, but speedy winger Corey Toole is more intent on helping the ACT Brumbies break a 21-year Super Rugby title drought.
ย 
ย 

ย 

Latest

canberra daily

SUBSCRIBE TO THE CANBERRA DAILY NEWSLETTER

Join our mailing lists to receieve the latest news straight into your inbox.

You have Successfully Subscribed!